... due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a... Decisions of the Department of the Interior - Page 110by United States. Department of the Interior - 1960Full view - About this book
| United States. Court of Claims - Claims - 1937 - 710 pages
...event the contractor should pay liquidated damages for the delay, ascertained as provided for, but was not to be charged with liquidated damages because...the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,... | |
| United States. Court of Claims - Law reports, digests, etc - 1941 - 858 pages
...completed or accepted the amount as set forth in the specifications, but that the contractor would not be charged with liquidated damages because of any...the contractor, including, but not restricted to, acts of God, acts of the Government, strikes, and unusually severe weather. This article further provided... | |
| United States. Court of Claims - Law reports, digests, etc - 1948 - 974 pages
...thereof : Provided, That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays...the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1952 - 936 pages
...proceed shall not be terminated or the Contractor charged with liquidated damages because of any delay in the completion of the work due to unforeseeable...of the Contractor, including, but not restricted to acts of God, or of the public enemy, acts of the Government, acts of another contractor in the performance... | |
| United States. Court of Claims - Law reports, digests, etc - 1943 - 906 pages
...pay * * * liquidated damages for each calendar day of delay," but with the proviso that he shall not be "charged with liquidated damages because of any...unforeseeable causes beyond the control and without the fault or negligence of the contractor * * *." The contracting officer's findings are challenged by... | |
| United States. Court of Claims - Law reports, digests, etc - 1948 - 886 pages
...proviso : Provided, That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays...unforeseeable causes beyond the control and without the fault or negligence of the con552 Reporter's Statement of the Case tractor, including, but not restricted... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1950 - 1004 pages
...the right of the contractor to proceed shall not be terminated under this Article or the contractor charged with liquidated damages because of any delays...completion of the work due to unforeseeable causes be891357—50 25 Reporter's Statement of the Case yond the control and without the fault or negligence... | |
| United States. Court of Claims - Law reports, digests, etc - 1946 - 920 pages
...thereof: Provided, That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays in the completion of the work due to unfore116 Reporter's Statement of the Case seeable causes beyond the control and without the fault... | |
| United States. Court of Claims - Law reports, digests, etc - 1943 - 672 pages
...project. I find that resulting from the circumstances hereinbefore stated, you were not delayed in completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the contractor. An extension of time for completion of the work will not be... | |
| United States. Court of Claims - Law reports, digests, etc - 1936 - 940 pages
...thereof: Provided, That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays in the completion of the work Reporter's Statement of the Case due to unforeseeable causes beyond the control and without the fault... | |
| |